Our Business School Will Be One of the Premiere Facilities in Indianapolis

Opening January 2018

View S2L3 live construction feed

  March updates:

Construction in the Physical Education (PE) Center began the week of March 27 with the closing of the main level restrooms and the basketball and volleyball locker rooms. Note that the restrooms on the lower level will still be available for use. 

  •  Center for Student Success in Life, Learning, and Leadership: Site work continues. This work includes the construction of new concourse restrooms and concession stand set to open this coming September. For our new Dining Commons, underground utilities and foundations will be installed, with components of the building’s steel structure just around the corner. 
  • Byrum School of Business: And we’re off! With steel going up, the building is beginning to take shape. The steel process is a major milestone in vertical construction because it means we are done with the ground work

Center for Student Success in Life, Learning, and Leadership

This new center will accommodate our extraordinary growth over the past 15 years, as well as future enrollment growth which we expect to grow significantly by 2025. The new center will include:

  • a dining hall
  • recreational facilities for intramural sports
  • new fitness facility
  • classrooms
  • meeting spaces
  • convocation center
  • a weight room, and more

  S2L3 will be completed in two phases. The expected completion date for phase 1 is January 2018. Phase 2 is expected to be completed in October 2018.

View the Phased Aerial Views of S2L3 (pdf)

athletic courts
fitness center

Byrum School of Business

Our new business school will house the latest technology and collaboration spaces in the state. Scheduled to open in January of 2018, we expect this new building to serve as an innovative space supporting our hands-on curriculum where students learn by collaborating with businesses.

  Construction began December 2016 with a target completion date of January 2018.

business school stairs render
business school outside render
business school interactive wall render

Where do I park?

During the first phase of construction, we will lose 60 parking spaces behind and between Clare Hall, Marian Hall, and Oldenburg Hall. The Office of Campus Operations is working to open up more parking spaces to replace the ones we will lose.

More parking will be lost in late May, when phase two construction begins and the university is developing an off-campus parking and shuttle plan for the Fall 2017 semester to accommodate the loss of parking.

What's moving where...and when?

Alternate spaces are in development to accommodate all students through the duration of construction on the Center for Student Success in Life, Learning, and Leadership. These spaces include:

  • Locker rooms, which will be constructed in the lower level of Clare Hall for use during the 2017-18 academic year. These locker rooms are scheduled to open in June 2017.
  • The athletic training department, which will relocate from the PE Center to the former campus operations building on the west end of campus. The Office of Campus Operations has moved to the lower level of Clare Hall. 

 

Turn a page, start a new chapter... #MakeItMarian

Get info Apply now

© 2017 Marian University
Notice of Nondiscrimination
Marian University does not discriminate on the basis of race, ethnicity, color, sex, gender, gender identity, sexual orientation, religion, creed, national origin, age or disabilities in the selection of administrative personnel, faculty and staff, and students.